|
-
Portofolio -
Ship
Repairs - RAYMOND CROZE PROJECT
-
-
On
Monday 4 August, the cable layer Raymond Croze sailed from the
shipyard after the completion of a very successful repair and
refit programme. This vessel is owned and managed by France Telecom
and the Malta Shipyards were pleased to have been awarded a major
contract by this prestigious company.
During this refit the vessel was drydocked in No4 dock and a wide
variety of work was carried out. The major items included:
The
existing Fwd gantry crane was removed and a new gantry crane was
fabricated and fitted. Electrical cables were partly renewed and
the light mast was lengthened.
An
Aft deck extension was fitted and a new generating set was installed.
This included electrical cabling and fuel lines.
A
new P.D.U. was installed.
A
Fwd deck extension was fabricated in-way-of the R.O.V. deck. All
existing R.O.V. equipment was removed and new more modern equipment
was installed. This included the fitting of a large pulley for
the umbilical cable, an umbilical winch, a winch hydraulic power
unit, an ROV, buoy davits, and an extensive amount of electrical
cabling. This modification also required the fitting of a larger
R.O.V. crane.
A
new R.O.V. console was installed in the computer room.
A
handling crane was fitted on the Aft area of the vessel.
Other
normal dock work including the propulsion machinery equipment
[mechanical & electrical], auxiliaries, cleaning of tanks,
external blasting and painting, was also carried out.
The
work proceeded exactly as scheduled and the Raymond Croze was
completed on time and to the satisfaction of the owners. All shipyard
employees who were involved in this project should feel proud
of a job well done!
Passenger
Liners - M/V MARCO POLO - 2003 REFIT
-
-
The
Norwegian Cruise Line Marco Polo successfully completed it's 2003
scheduled refit and repairs at Malta Shipyards.
Background:
This cruise ship was built in 1965 and was christened Alexander
Pushkin by her Soviet owners. Purchased in 1991 by Orient lines
because of her classic profile and ice-strengthened hull, the
vessel was re-built and re-named Marco Polo. The ship specifications
are as follows:
Tonnage: 22,080 GRT
Length: 578.4 ft
Breadth: 77.4 ft
Draft: 26.9 ft
Speed: 20.5 knots
Passenger Decks: 8
Number of passengers: 826 double occupancy
2003
Refit:
The Marco Polo entered Valletta Harbour on the 3 October 2003
and went directly into No 4 Dock of Malta Shipyards. Work commenced
immediately as the refit and repair schedule was extremely tight.
The main work items during the refit were:
-
Installation of bow thruster - The old bow thruster was removed
and hull penetrations were prepared for the new bow thruster tunnel.
A new bow thruster complete with tunnel was installed.
-
Repair of damaged Hull bottom - On drydocking the extent of bottom
steel damage was assessed. Approximately 20 tons of steel were
replaced. This necessitated the removal of 70 tons of permanent
ballast in the form of steel ingots, which had to be replaced
on completion of the steel repairs.
-
Port Shaft Repairs. - The port shaft was disconnected, withdrawn
and removed to the engineering workshop for machining. When complete
it was returned to the vessel and refitted with new seals.
-
Port Propeller Repairs - The Port propeller was removed ashore
for contact damage repairs. The damaged blade tips were renewed
and after polishing the propeller was returned
-
Blasting and Painting - An area of external hull was blasted and
painted. Surface preparation was carried out using a combination
garnet blasting and low volume water system that achieves SA 2.5
standard and is completely dust free. This allowed the rest of
the dock work to continue without interruption.
-
Rudder and steering gear repair - The rudder and steering gear
were overhauled. The steering hydraulic pumps were removed to
the workshop for repairs.
Other
work, such as: renewal of several piping systems; overhaul of
port and starboard stabilisers; main engine repairs; installation
of new bridge navigational equipment; and the overhauling of sea
valves, was also carried out. During the refit, several subcontractors
were also engaged in upgrading work of the passenger areas.
The
Marco Polo left Malta Shipyards on the 14 October as scheduled.
The planned scope of work and a significant amount of additional
items that developed had been completed during this refit. The
Miami based technical management of the Norwegian Cruise Line
expressed their satisfaction with the shipyard performance and
praised all those involved for their commitment and workmanship.
Conversions
- IKDAM FPSO CONVERSION PROJECT
- -
On
the 4 October, 2001, the IKDAM FPSO, converted from the former
M.T. Northia, sailed from Malta Drydocks to undergo sea trials
before taking up station on the Isis field off the coast of Tunisia.
This marked the successful completion of the conversion project
the contract for which had been awarded to Malta Drydocks by Brovig
RDS of Aberdeen in January 2001 following stiff competition between
a number of shipyards.
The
project began in February and the work-scope involved the removal
of the bulbous bow, extensive hull modifications for the connection
of the patented Tripod Catenary Mooring System (TCMS), installation
of new generating capacity, fabrication and installation of a
helicopter deck, process deck, flare stack and bow cantilever
and gantry, full hull blasting and coating, upgrading of accommodation,
fire fighting and life saving systems and equipment and modifications
to the propulsion system. The topside facilities, supplied, installed
and commissioned by Expro Production Solutions, included an oil
production plant which can process up to 30,000 bopd and a 3 mmscfd
gaslift system.
The
successful completion of this contract marked the return of Malta
Drydocks to the offshore market after an absence of nearly twenty
years. Peter Moore CEO of the Malta Shipyards stated that, the
completion of this contract clearly indicates to the market that
Malta Drydocks has the capacity and capability to execute complex
offshore engineering projects successfully without any compromise
in safety or quality. The integrated project team has done an
excellent job and the shipyard workforce has proved what it is
really capable of. The project, which has not been without its
challenges and difficulties, was also carried out concurrently
with a second major refit contract, which was completed ahead
of schedule. I am pleased to confirm that we are ending the project
with the same philosophy with which it began, that of true partnership
between the client and the contractor.
Willem
vant Spijker, President of Coparex International commented:
We are extremely pleased with the quality end product which
was delivered by MDD despite material adverse circumstances beyond
their control. Their positive, professional approach throughout
this project has been a decisive factor in its ultimate
success."
Offshore-
ACTINIA
-
-
It
is some years since Malta Drydocks competed in the market for
offshore drilling rigs, however, the shipyard has demonstrated
that it is capable and has the resources to supply a competent
and useful service for offshore drilling companies. In March/April
2002 Malta Drydocks successfully completed, ahead of schedule,
a contract for the international drilling company Transocean Sedco
Forex. The contract was for 22 days and the base scope work was
completed within 18 contractual days, with the rig departing at
TSF's convenience 24 days after arrival.
TSF's work scope was basically for the semi-submersible drilling
rig 'Actinia' to have an 'ABS' class survey undertaken with additional
work including but not limited to the following:
- The
replacement of all 8 fairleaders. TSF had elected to have new
fairleaders manufactured and installed, as opposed to reconditioning
the original fairleaders.
- Replacement
of the low-pressure mud system between the mud pits and the mud
pumps.
- Replacement of selected under deck walkways and column ladders.
- Manufacture
and installation of a new crane boom rest.
- Replacement
of valves in high-pressure mud manifold and the standpipe manifold.
- Fabrication
of two new stand pipes.
- Overhaul
of pontoon hydrophones and pontoon side valves for the hydrophones.
- Replacement
of a section of the diverter pipe.
- Circuit
breaker replacement on main and emergency switchboard.
The work proceeded exactly as scheduled and the Raymond Croze
was completed on time and to the satisfaction of the owners. All
shipyard employees who were involved in this project should feel
proud of a job well done!
The
work was undertaken with the yard being fully utilised for ship
repair, and completed with full quality control, NDT, and documentation,
to Transocean Sedco Forex's satisfaction.
"MDD
project team have worked closely with the TSF team assigned to
the project. The co-operation and effort have been well appreciated"
said Claude Gabillard TSF Manager of Projects.
|